Repackaging a Finished Good
Question:
How do we split a finished good to repackage as a different finished good?
Answer:
 The best way to handle this is to use a Production Order. Here are the steps to repackage a finished good using a Production Order:
- Go to Production>Production Order
- Enter the item number you are producing in the header
- In the components, change your Bright Beer item to the item that you are removing from stock
- The Planned Quantities will default to a 1-to-1 ratio. Update the Planned Quantities to match what you are actually going to issue and receive.
- Add the Production Order
- Process the PdO the same way you would do any other production
Example:
In this picture, I am taking one 1/2 BBL keg of Amber Ale and turning it into three 1/6 BBLs